patching...
Welcome back, Patch Blogger!

PSE&G Power Line Work Starts Without Final OK

Instead of starting work on $790 million project before getting final approval, how about clearing trees along power lines?

 

Construction has begun on Public Service Electric and Gas Co.'s transmission line upgrade through Northwest New Jersey.

That would seem to be slightly premature, as the National Park Service still technically has not given final approval for the work—upgrading the existing 230-kilovolt transmission line for about 45 miles, adding 500 kilovolts onto towers that would be as tall as 195 feet in some cases.

The park service's approval is only for its property, but it is still critical, given the line runs smack through the Delaware Water Gap. And while the NPS won't make a final decision for at least a month after releasing its environmental impact statement—expected sometime this month—its approval appears to be a given.

Still, it has not been granted and legal appeals are pending, as well.

The line is, however, already way behind schedule: When PSE&G initially proposed it, officials estimated it would have been completed by now.

So the utility announced it has begun preliminary work in Andover Township, Boonton Township, Byram, Jefferson, Hopatcong, Kinnelon and Montville. The work, which ranges from surveying in some places to site clearing and grading and foundation drilling in others, will continue through the end of the month.

The idea of clearing trees and other vegetation, as well as drilling, does not sit well with environmentalists and others who have been fighting the project for years. They were angered by the NPS' reversal earlier this year of its initial determination that no work would be best for the park after PSE&G agreed to pay roughly $40 million to compensate for any loss or damage to parkland.

Opponents contend the upgrade is unnecessary. They point to a decision by PJM Interconnection, the regional transmission organization, just last month to delete two other projects in the Mid-Atlantic states from its plans. The economic downturn had brought a reduction in the demand for electricity, negating the need for the projects. That has happened in New Jersey, too, according to opponents.

But PJM says nothing has changed the need for the upgrade of the line from Susquehanna, Pa., to Roseland. What's the truth? Supposedly the work was needed to prevent power outages. There were none this year. That doesn't mean there won't be any in the future, but so far, PJM's predictions have not come true.

Opponents say the dice were stacked against them from the start, including the agreement by the Obama administration to place this project on the fast track. That was further proven when the NPS changed its mind from preferring a no-build alternative to the current route upgrade. They also complain the work supports the continuation of dirty coal power by bringing it to New Jersey and beyond, when the state and nation should be looking toward cleaner alternatives.

It seems unquestionable that massive towers will mar the beautiful viewscapes in many places. How dangerous the lines are remains in question, with experts arguing on both sides of the issue. Construction will damage wetlands and other natural areas. But if that's what it takes to prevent widespread blackouts, isn't it worth it?

Right now, the only thing standing in the way of full construction is the final park service decision, unless the opponents can convince a judge to issue an injunction while the case works its way through the courts. PSE&G obviously thinks the odds are in its favor, given it has started work. It would be a huge waste of money, not to mention environmental gems, if they're wrong.

But don't forget that it won't help anyone if the electricity that travels along these massive wires from Pennsylvania can't get to individuals' homes because tree limbs bring down the lines to neighborhoods and homes during storms like the two North Jersey faced last year.

Isn't burying some lines and clearing overgrowth along others, which clearly need to be done regardless of demand, where utilities should be putting more of their resources now?

Related Topics: PSE&G and Susquehanna-Roseland
Should PSE&G be proceeding with the transmission line work before getting final approval from the National Park Service? Tell us in the comments.

Bruce

9:46 pm on Sunday, September 16, 2012

Nothing but arrogance from PSE&G / PPL! They have started construction without final approval, and nobody seems to be stopping them, or at the very least checking to see if what they are doing is within their legal limits. Are they above the law? Do they not have to abide by the rules like everyone else? It sure would be nice if state / local authorities would check it out!

Reply

The Stig

12:06 am on Monday, September 17, 2012

For those who say this upgrade is unnecessary, why would a company spend tens of millions of dollars if it didn't have to? As for your final question - What if they spend all their money upgrading a few small areas, but their long distance transmission capacity isn't sufficient to supply those lines or their millions of other customers? The needs of the many outweigh the needs of the few.

Reply
Comment_arrow

Michael Brancato

8:22 am on Monday, September 17, 2012

Stig, I don't think the issues that AN upgrade isn't necessary, it's more that THIS exact upgrade isn't necessary. Instead of spending millions running wires through a national park from a coal burning plant, PSE&G could be spending that money building wind turbines or solar facilities that would bolster the power in this area without the need for outdated technology. Instead of looking to the future, PSE&G is holding on to the past. They may make a few more dollars today, but it will cost more in the long run as the price of coal and oil continues to rise.

Comment_arrow

Beth Ann

12:40 pm on Monday, September 17, 2012

PSE&G would spend this money because they have a guaranteed rate of return on the investment, irrespective of whether the line is needed or not. They get their investment returned plus they get a return on their investment. Why not?

Comment_arrow

The Stig

5:31 pm on Monday, September 17, 2012

The electricity still has to get from where it is generated to where it is consumed, so it has to run through somebody's back yard. As for wasting money just to make money, that's another Lib myth. No one is building transmission lines unless they can make a return because of the volume of electricity running through them.

Comment_arrow

spokey

11:26 am on Tuesday, September 18, 2012

"Supposedly the work was needed to prevent power outages. There were none this year. That doesn't mean there won't be any in the future, but so far, PJM's predictions have not come true."

Funny. I've had several outages this year. Perhaps the writer can send me some of his juice.

For those suggesting wind; stig is right. There still needs to be transmission. Oh, and I assume you all have switched your electricity to the higher cost 'green' choices. If not, seems a bit hypocritical.

Finally, this stuff can take years. I don't necessarily trust PSE&G not think they are particulalry well run, but our electrical grid is a disaster. The interconnects are ancient technology etc. I don't know that this addresses any of this, but we need the job done.

Personally I favor micro-nukes which should reduce some of the need for massive transmission lines. But I'm guessing most of you don't want that low cost, efficient, power generation either.

Comment_arrow

The Watcher

12:04 pm on Tuesday, September 18, 2012

PSE@G is not spending it's money it's spending OUR money. The profits will go back to IT's shareholders not us. Spokey your outages were caused by the weather not by shortages. What is the half-life of your mini-nukes? "The company will NOT lose money on the purchases, regardless of the result of the power line proposal. Because the Susquehanna-Roseland plans have been described a "reliability" project, PSE&G will be REIMBURSED by the Federal Energy Regulatory Commission"

Comment_arrow

spokey

1:00 pm on Tuesday, September 18, 2012

watcher, you are correct about the weather. But then again we are asked to conserve during heat waves. Asked to turn off air conditioning while at work, etc. The electric company offers discounts for people who will install smart meters, allow the company shut down their air conditioners if needed etc. Seems to me all that indicates shortages.

I don't know anything about mini-nukes or even if there is such a thing. The life span for micro-nukes is around 30 years. Some info on a Toshiba proposed for Galena AL. http://en.wikipedia.org/wiki/Toshiba_4S

Comment_arrow

The Watcher

1:30 pm on Tuesday, September 18, 2012

Spokey this energy is going to NYC not to NJ at no cost to the power company, and all the profits to the stockholders, not the people who have to look and deal with the over 180 ft high towers that have to be fixed with a guy hanging off the side of a helicopter. As for the micro-nukes (sorry I typoed mini) you are left with storage of radioactive material for 30 years (according to your source). BTW wikipedia is not allowed in schools as resource material.

Comment_arrow

spokey

2:36 pm on Tuesday, September 18, 2012

watcher;

"Spokey this energy is going to NYC not to NJ "

One of our country's problems is the rampant parochialism. Although I don't have much use for NYC, other people do. including NJ dwellers. And I'll bet even some of those near those power lines.

"wikipedia is not allowed in schools as resource material."

Good thing I'm not currently in a school then<g>. Seriously, though I agree it often has mistakes, but then again so does every other resource I use. And I'd be really surprised if every last school of any kind in this country bans the use of wikipedia. So rather than an ad hominen attack on wikipedia (hmm is that even possible?), perhaps you could point out the errors for the edification of us all.

Comment_arrow

The Watcher

5:33 pm on Tuesday, September 18, 2012

Spokey I was not attacking you. As far as NYC, do we really need all those advertising lights? That electricity is not being used to do work or for air conditioning etc. As for Wikipedia I was hoping you could give us more information from other more generally acceptable sources. I for one am not for burying more radioactive materials, we've had enough radioactive accidents already. We have radioactive materials washing up on the shores of the West coast now.

Madison Station

7:35 am on Monday, September 17, 2012

Totally disagree with this opinion. They are clearing trees and shrubs from an EXISTING right of way. There are already power lines, and a somewhat clear path underneath them, along this right of way. These power lines have been in existence for many years before most of the residents along the line have been - which means they purchased land against the right of way with knowledge that power lines (and the associated, to be debated, effects of EMF) were present.

Personally, I think the new lines will look a lot nicer. Instead of using mini Eiffel towers they'll be using monopoles (I believe) which are less visually cluttering. I think they're also combining what used to be two separate towers onto one pole - again less of an impact on the sight lines.

Give it up. This is good for 99.9% of the population, especially as we enter the "plug-in hybrid" trend resulting from ridiculous emission standards. Sure, let's power our cars with dirty coal. Yay! At least when we flick the switch we'll still have power...

Reply
Comment_arrow

STATE PARK

8:19 am on Monday, September 17, 2012

put it in your yard then if you like it so much

Comment_arrow

Bruce

9:20 am on Monday, September 17, 2012

Check your facts! Monopoles in some areas, yes, but (to use your terminology) huge Eiffel Towers that are more than twice the size of those already in place in many other areas, including the ones that run through Jefferson Twp. And, how is this good for 99.9% of the population when the additional capacity is not needed? Power usage is down and predicted to decline. PJM stated brownouts / blackouts by 2012 if these weren't built by then... has that happened? NO!

Comment_arrow

The Stig

5:33 pm on Monday, September 17, 2012

For all the NIMBYs - Please disconnect yourself from the grid BEFORE you come here and whine. Then you might have a case. As long as you are sucking in power, you have no grounds for complaining.

Comment_arrow

Madison Station

10:45 pm on Monday, September 17, 2012

Power usage is expected to decline? Umm... an uptick in the economy when Romney gets elected and emissions standards leftover from the Obama administration that force all carmakers to make plug-in hybrids mainstream will cause extreme levels of power brownouts, blackouts and unaffordable prices.

Comment_arrow

Madison Station

10:51 pm on Monday, September 17, 2012

Bruce - Jefferson Twp. isn't exactly a quaint town. It has out of control commercial sprawl and some seedy businesses. Furthermore, I can't believe the state Ok'd two traffic lights on Rt. 15. That is 10 times worse to me than larger electric line towers. Another 3 days of my life wasted so some idiot can make a safer left turn onto a one way road.

Comment_arrow

Denobin

12:58 pm on Tuesday, September 18, 2012

@ state park: If oyu bought a place next to an existing right of way you have to suck it up. It's like the bozos who buy an estate next to a farm for the "country living" and then complain about the smell. Too bad.

Comment_arrow

Bruce

4:07 pm on Tuesday, September 18, 2012

O.K., I'm going to venture into VERY dangerous territory here... here goes... don't count on Romney (if elected) to turn the economy around, at least not anytime soon. I'm not a big fan of the Dems, but you may recall the economic meltdown came to a head under Bush Jr. (Republican) and as he was exiting office after 8 years. As for those traffic lights on Rt. 15, if you live here and travel that road as much as I do, you should appreciate them... can't tell you how many times I've almost been creamed at those intersections on the northbound and southbound sides!

Maxim Sapozhnikov

8:37 am on Monday, September 17, 2012

Fast track? Why am I not surprised? $200,000 contribution from Exelon buys a lot of good will from Obama. I haven't seen such a brazen pay-to-play even with Bush.

Reply
Comment_arrow

The Watcher

11:25 am on Monday, September 17, 2012

This is not the first story about the lines. I believe the Herald called it "hush money" when PSE&G came through to buy the land they needed. Other towns refused needless to say (again) we took the money without a vote.

g

9:14 am on Monday, September 17, 2012

Why can't these power lines be buried underground?

Why can't all power lines be buried underground.?

Everytime we have storm power lines are knocked down and families are without electricity for days and weeks.

Reply
Comment_arrow

Bruce

9:24 am on Monday, September 17, 2012

They can and should be buried, but that would be more expensive than using the existing right-of-way and methodology currently in place. It's all about dollars and cents / profits for big business and certainly utilities, and in their case without regard for, among many other things, environmental impacts.

Comment_arrow

Madison Station

10:37 pm on Monday, September 17, 2012

And what happens when it floods? The power goes out.

Comment_arrow

The Watcher

11:43 pm on Monday, September 17, 2012

The "new" lines need to be worked on while they are still live by a man hanging off the side of a helicopter.

Comment_arrow

Edward P. Campbell

7:37 am on Wednesday, September 19, 2012

Bruce – Yes, Yes, they can and should be buried! However, if they were to do that, you wouldn’t be able to afford your power bill, unless of course you’ve busted you behind, worked hard, acted thrifty, invested wisely, and became one of those ugly one percenters!

Beachbum

11:00 am on Monday, September 17, 2012

Go stop the www.stopthelines.com and look at their "printable flyer". There is a wealth of information as well as an illustration of exactly how these towers will appear. It is an eye-opener. This power line is NOT even designated for our use, it is for NYC yet it is our community that will be blighted by its path. The arguments against this line are too numerous to include here. It is good to see more people recognizing it now but this opposition has been ongoing for a couple of years. I can only hope that this can still be stopped.

Reply

Dan the man

11:12 am on Monday, September 17, 2012

My old jeep dirtys the envroment every time i hit the gas and i cut mad trees down so that cant do more harm than me lmao

Reply

NJSquatch

12:30 pm on Monday, September 17, 2012

It is all about the bottom line. The electricity will be generated in PA which is much more coal friendly. One could assume that coal plants are much cheaper to operate over the local natural gas plants, despite being more efficient. These lines will allow them to run the coal plant at full throttle, providing PSEG cheaper electricity that they can turn around and sell to the consumer at the same retail rate. $$$$

Reply
Comment_arrow

Beth Ann

12:44 pm on Monday, September 17, 2012

Coal plants are not cheaper to run than natural gas plants, now that there is abundant gas from the Marcellus Shale. There just aren't any enough natural gas plants in NJ right now.

Comment_arrow

The Watcher

1:04 pm on Monday, September 17, 2012

Beth Ann perhaps you didn't see the documentary on tap water that you could set fire to, and now they have to truck in water to drink. http://marcellusprotest.org/the-big-deal-about-marcellus. PSE&G plans to send the electricity to NYC where they can charge more money. It will not benefit NJ.

Freda's Sugar Daddy

7:22 pm on Monday, September 17, 2012

It's not like they are pouring raw chemicals into those fantastic Jefferson streams that noone even notices. Does this project provide jobs for NJ? This article is redundant. Those crews are trimming trees on property owned by the power co. Just as you would trim your tree in your back yard. Electricity is the # demanded item in this country after food and fuel. With the internet so controlling our lives those tower upgrades are necessary. People are complaining about environmental issues yet plug there coffee pots, wireless routers and DVR's into there walls everyday. Find another topic please.

Reply
Comment_arrow

Bruce

9:26 pm on Monday, September 17, 2012

Trimming trees? You are soooo sadly mistaken if you think that's all they are doing! There is heavy rock-splitting equipment already working in the right-of-way in Jefferson, so a wee bit more than just "tree trimming." And, please explain what the "internet so controlling our lives" has to do with "those tower upgrades being necessary." You lost me there!

Comment_arrow

Freda's Sugar Daddy

4:52 pm on Tuesday, September 18, 2012

Bruce. Where do you think we get electricity from? A wall outlet? You must be from Jefferson.

Comment_arrow

Bruce

5:40 pm on Tuesday, September 18, 2012

Freda's Sugar Daddy - How the heck does your comment back to me have anything to do with the subject at hand?? And, I AM from Jefferson, and weez up in deez here parts git are 'lectric from hampster wheels! Get serious, please!

Overland Legalectric

9:16 pm on Monday, September 17, 2012

Here it is, 2012, when they threatened us with blackouts, freezing in the dark, and they've had no problems whatsoever. MAPP and PATH were cancelled... DUH, where is the need? PJM wouldn't dare look at it because it so clearly isn't needed, just wanted for more profit. How DARE they!

Reply
Comment_arrow

Bruce

9:32 pm on Monday, September 17, 2012

Correct! The only time we lose power is during a storm when trees along right-of-ways in need of maintenance fall on their lines. Hey... here's an idea! How about taking some of that $1.2 billion earmarked for this project and doing a little housekeeping along the right-of-ways? This way, we wouldn't lose power for 2 - 3 days at a clip! And, gee, if they'd hire more crews to do this, they would actually be creating jobs! Naaaah... makes too much sense, now that I think about it!

The Watcher

10:30 pm on Monday, September 17, 2012

PSE&G buying local properties saugenstein@njherald.com
As the Susquehanna-Roseland power line issue buzzes through northwestern New Jersey, PSE&G has made some tactical land purchases along the 45-mile route -- at no likely financial risk. The power company has bought three properties along the route, totaling more than $2 million and 150 acres. A fourth is under contract, but awaiting a closing. Two of the four properties are houses -- one was a Fredon home directly beneath the existing power lines that sold for $535,000 in December, and the latest one under contract is a house on Larikat Lane in Sparta. The owner of the Larikat Lane house is in the process of leaving the house, but declined further comment about the sale price. The company will NOT lose money on the purchases, regardless of the result of the power line proposal. Because the Susquehanna-Roseland plans have been described a "reliability" project, PSE&G will be REIMBURSED by the Federal Energy Regulatory Commission for any such land or home purchases -whether or not the application is approved by the state's BPU. "We are purchasing these properties now to ensure that we can meet our in-service deadline of the summer of 2012," said Karen Johnson,for PSE&G. Energy commission spokeswoman confirmed 100 percent reimbursement, but would need to be approved on a case basis for PSE&G's plan. Johnson also said profits of any properties PSE&G would resell at any point would be credited to the company's ratepayers.

Reply

Andy Thompson

9:29 pm on Tuesday, September 18, 2012

At some point old infrastructure needs replacing so eventually the towers will need replacing OR the wires go underground. PSE&G could put the lines in the ground using the existing right if way if they wanted, of course in NJ that may involve rock excavation which is expensive. And funnily enough in other places they don't fail when it rains, amazing eh. Question is whether the current plans are necessary, probably not right now. Trimming and local underground work would be more effective for the bill payers, but not the shareholders of course.

Reply
Comment_arrow

Madison Station

10:42 pm on Tuesday, September 18, 2012

Do you know if it's even possible to bury 500kv lines? I see rocks exploding from steam pressure when things heat up...

Edward P. Campbell

7:30 am on Wednesday, September 19, 2012

PEOPLE – Get a grip! Why is it so many Americans are more than happy to spend 50 or 60 grand on a luxury car, but think the luxury of the best health care in the world, or the luxury of a reliable power system should be free to us?

Get a GRIP! THINK!

Reply

Edward P. Campbell

8:11 am on Wednesday, September 19, 2012

GOOD NEWS – All of you who think the “Shareholders” are making out so well in PSE&G, now you too can be a shareholder for just $31.39! Jump in get rich!

Reply

The Watcher

11:39 am on Wednesday, September 19, 2012

We do not have PSE&G we have JCP&L NYC is getting the electricity and we are getting the lines and all that goes with it.

Reply

PJ_Wolf

8:26 pm on Wednesday, September 19, 2012

The rich get richer and the little man has less and less of a voice, too many fat cats and politicians/oversight boards in bed with private sector corporations - the "American" way. Queensryche said/sang it best......

Reply

The Stig

10:50 pm on Wednesday, September 19, 2012

Burying lines under ground costs a fortune, and repairing them when they fail can be very time consuming and much more expensive. All these costs are borne by the rate payers. Same for the loss of electricity when the lines go out.

If you want power companies to stop increasing their transmission capacity, stop using more electricity! Get rid of your AC, fridge, TVs, PC, lights and other non-essentials.

Reply
Comment_arrow

Joseph Keyes

11:11 pm on Wednesday, September 19, 2012

The topography of our township presents significant challenges for underground electrical service—i,e., $$$ . Some homes in the township have such service because developers absorbed the costs of providing it. The rest of us depend on power hanging from poles, subject to wind, ice, and snow.

Comment_arrow

The Watcher

11:42 pm on Wednesday, September 19, 2012

The lines have to be worked on while they are still LIVE

EMG

8:01 am on Thursday, September 20, 2012

I live over on Schneider and the work they are doing is so loud. Its bad enough that they are even doing it to begin with, but starting at 7am and ending at 5, all I hear is LOUDNESS. Add to that the workers screaming at each other above the machinery noise, including the F-bomb dropped at least 20 times each day. The whole thing sucks.

Reply

CAE

10:15 am on Tuesday, November 6, 2012

Regardless of how I feel about this project, I can not help but question why it went back into full swing immediately following the storm, given there are so many PSE&G customers still without power.

Reply
Comment_arrow

Bruce

12:20 pm on Tuesday, November 6, 2012

Would love to hear how PSE&G justifies this! Certainly tells you something about their priorities, eh?

shenhuang

1:05 am on Monday, December 3, 2012

When a giant statue of Confucius http://www.coachfactoryoutletcc.us/ Coach Outlet Online suddenly appeared in Tiananmen Square, not far from Mao's iconic portrait early last year, tongues wagged http://www.guccibeltsoutletstores.net/ Gucci Belt about what it all signified politically was Confucius back to dislodge Mao as China's spiritual leader?The http://www.coachoutletonlinewo.com/ Coach Factory Outlet statue was moved off the square just as abruptly a few weeks later, prompting some in political circles to http://www.coachfactorystoredo.com/ Coach Outlet Store Online joke that the venerated sage, who hailed from rural Shandong, had been busted for not having a Beijing http://www.coachfactoryoutletpo.com/ Coach Factory Outlet residence permit.On Wednesday, a woman who took our call at the website's office in Beijing insisted that http://www.coachoutletonlinefc.org/ Coach Outlet Online it was "impossible that the People's Daily would quote from any unreliable media we do verify our news and http://www.coachoutletwr.com/ Coach Online Outlet sources.The woman, who declined to identify herself, said the story and pictures had been removed a day after being http://www.coachoutletloa.com/ Coach Factory Online posted.

Reply

Leave a comment